Wednesday, December 5, 2012

Day #115 - Lots Happening!

Lots is going on at the house today.  Miles of Action Door installed the garage door.  It is a factory finish that will not ever have to be painted.  Once the green trim is on, it will look great and it matches the window frame color!


The plastic over the front entrance is to protect the newly poured and stained concrete entryway.

The Harmony Gardens crew continues to work on the retaining wall.  The insulator has finished insulating the attic.  The HVAC guys will begin installing the geothermal heat & AC unit soon.  Tom from MWM Cabinets measured up the shower in the master for the solid surface shower walls.

The Valerian crew began laying the tile in the two bathrooms and utility room today.


I selected the grout today, and it is on order now.  I also picked out the river rock floor for the master shower as well as the grout today.