Again, it was another day of excellent progress.  I received a phone call from Thomas of the Photo Den that he would arrive at 9:30 to do the pre-wire.  While I was talking with him, Tony & Jay from Kennedy Fuel arrived to work on all the exhaust systems and gas fireplace.

Dan & Sam from Valerian were also on site all day hanging the last exterior door and working hard on finishing the siding.

By the end of the day, all the exhaust ducts were installed and hooked up for the range hood, dryer, two bathroom exhaust fans and the water heater.  Also, the holes were cut and pipe installed for the gas fireplace.  The pre-wiring for TV, surround sound, and Internet were finished, and Dan & Sam had made significant progress on the siding.

As a side note, you do not ever know what you will find on a construction site.  We have had a couple of visitors that have hung around for 2 days, and we are not sure when/if they will leave.  According to Dan & Sam, their names are Stu and Stuie.  See their photo below.



These guys are so comfortable that you can walk within 3 or 4 feet of them and they are not frightened.  And, they have found a swimming pool that they really like.



We have no idea where they came from, but they have a new temporary home now!