Saturday, January 19, 2013

Day #160 - Darned Close!

I was in Las Vegas for a week; so, I was anxious to see the progress that has occurred.  The exterior paint is almost complete with just a couple of small areas that need finished.


Lots has happened in the interior.  All the door hardware is installed, the back splash is in the kitchen but needs grouted.  I picked that out today, and it will be finished Monday.  This photo did not turn out all that well unfortunately.  It looks much better!


The kitchen is coming together.  The cabinets and pantry are finished and in place.  The range will be installed after the grout is finished.  The range hood is awesome!  Commercial grade.


(Yes, I should have moved the box and my coffee cup!)  The LED tape lighting under the cabinets is fantastic!

All the faucets are installed in the kitchen, baths, and utility room, and the geothermal heating/cooling system is operational.  The thermostat was set at 65 degrees, and the house seemed very toasty.  This system should be wonderful!

Talking with Alan, he said the final inspection and energy test by the Energy Trust of Oregon are both scheduled for Tuesday, and I am to get the keys Thursday!  The moving van is scheduled for Friday! Talk about excited!